Clash Rule Export - imports only some clash rules not all

2 REPLIES 2
Reply
Message 1 of 3
jkirk00
484 Views, 2 Replies

Clash Rule Export - imports only some clash rules not all

During attempts to export clash rules from project to project, only the first 5 or 6 clash rules actually import into a new project. No errors, the rules just don't come into the new project during the import. Any suggestions?

2 REPLIES 2
Message 2 of 3
MichaelBussiere2
in reply to: jkirk00

Thank you for your post.  As of right now I am not aware of a limitation in the rules as described.  For reference I have included our document from our expert regarding clash rules, setting them up, and best practice.  This also includes a video he has created that is embedded in this blog post.  Please review, verify steps, and apply as needed.  If after verifying the steps, the issues should still persists, please attach a sample file for testing to see if there may be a link to the file(s) themselves.  Please keep us posted in the community.  Thank you

 

Clash Rules:  http://beyonddesign.typepad.com/posts/2012/08/using-clash-rules-in-navisworks-to-reduce-false-positi...



Michael Bussiere II
Support Specialist
Product Support
Autodesk, Inc.
Message 3 of 3
jkirk00
in reply to: jkirk00

Resolved by not exporting and using a NWF with the rules already in as a template to start new projects.