Recently we received an update in Schedules tool which allow user to commit to a task or milestone in a workplan. We found it a great update, but we noticed although when re-planning a committed task/milestone, ACC asks us to enter the new data and the root cause for the change, but after the change, there is no way we can see the history and the re-planned dates. We would preferably want to have that history visible both in the task/milestone panel itself but also a marker (such as a red dot or something) on the swimlane view. This help us to visualize , how many times that specific committed task/milestone was replanned and from which dates it was replanned. We can re-use such a data to later improve our planning for next projects. But we need to have access to those historical dates. Thanks in advance.