Message 1 of 2
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report
[ FlexSim 22.2.0 ]
I am building model for just time concept for assembly line, in which i am have to deliver loaded pallet at assembly station and pick up the empty pallet from station and unload that pallet to super market.
I am able to compete model using process flow. But I am not able to unload the pallet to supermarket once the task executer complete the look . Can you help
Model Name ( JIT Simulation 2 Part )
Solved! Go to Solution.