Hi, I am new to FlexSim. According to the setup shown in the picture, I have configured a trigger so that when the MoldingFloor content reaches 50 items, the MeltingProcess1 should start. I have also added a working schedule to the model.
Now, I want the MeltingProcess to start only after the MoldingFloor reaches 50 items, and it should begin at 8:30 AM on the following day—not in the middle of the current day.
How can I set this up in FlexSim?