I am trying to simulate a normal working day in my simulation with hours worked between 8am and 4pm. When 4pm comes around an operator is in the middle of completing its task sequence. I want the operator to stop working the moment the clock passes 4pm and restart on the task the next morning at 8am. How can I achieve this?

I have attached my current model to this question for you to take a look at.

Important to note that the task sequence the operator is undertaking is a co-ordinated task sequence generated at the queue 1.

baseline-rev-7-simplified.fsm

Thanks for taking the time to take a look at my question,

Harry Hart

0 Likes
Accepted solutions (1)
161 Views
1 Reply
Reply (1)
Message 2 of 2

gilbert_jerald
Not applicable
Accepted solution

@harrison hart

i have attached your model by doing some modification as per your idea have a look on it

T2622-baseline-rev-7-simplified.fsmhank you