Hello, I am new to Flexsim and I need to simulate an automatic loading arrangement of 24 pallets on 2 trucks, which make 12 daily trips.

maximum loading time: 35 minutes and maximum loading time to truck T1: 5 minutes.

Maximum charging time: 31 minutes (low season) - 43 minutes (high season) - 37 minutes average charging time. Maximum loading time to truck T2: 6 minutes

I must reduce loading times and increase the ramp loading factor system by 50%. I have production per month, but I can't raise in Flexsim 23.01.08

Thank you for your cooperation

0 Likes
692 Views
6 Replies
Replies (6)
Message 2 of 7

jason_lightfoot_adsk
Autodesk
Autodesk
Please refrain from posting duplicate questions
0 Likes
Message 3 of 7

Jeanette_Fullmer
Community Manager
Community Manager

Hi @Jpino,

It's hard to know how to help without looking at your model. To receive a more accurate solution, please post your model or a sample model that demonstrates your question.

If your model contains sensitive information, you could first toggle your post as private using the "make private" option under your question's "gear" menu. Private questions are visible only to site moderators. You can also contact your local FlexSim distributor for phone or email help.

0 Likes
Message 4 of 7

Jpinoe
Not applicable
0 Likes
Message 5 of 7

jason_lightfoot_adsk
Autodesk
Autodesk

It looks like you haven't done the tutorials - where are your pallets? Where do you define how many items should go on a pallet? Why do you process over 1 million items?

I can shed some light on the last question: For each token (109 in the first arrival) you are looking up the quantity to create in the global table - but this is already done using the quantity field in the source - so you'll create 109 squared items - 11,881 in the first arrival event .

0 Likes
Message 6 of 7

jason_lightfoot_adsk
Autodesk
Autodesk

Hi @Jpino,

We haven't heard back from you. Were you able to solve your problem? If so, please add and accept an answer to let others know the solution. Or please respond to the previous comment so that we can continue to help you.

If we don't hear back in the next 3 business days, we'll assume you were able to solve your problem and we'll close this case in our tracker. You can always comment back at any time to reopen your question, or you can contact your local FlexSim distributor for phone or email help.

0 Likes
Message 7 of 7

Jpinoe
Not applicable

gracias, logré desarrollar

0 Likes