Hi All,
- I created a road centreline alignment and offset alignments that are dynamically linked. Why is it that when I create kerb returns they do not link back to the tangent points but are still projected towards the intersection?
- When attaching a subassembly to the offset alignment that includes a kerb profile and pavement I want the pavement to target my road centreline. When I go to corridor properties I have the option to target the edge of pavement however it wont let me target alignments (road centreline). Cheers
Example below drawn in cad
Solved! Go to Solution.