Hi,
I imported an existing sanitary sewer network with a lift station to SSA.
It consists of gravity mains, a storage node & three pumps (a lift station), and a couple of force main, ending with an outfall.
However, I get an error message (ERROR 119) when I make the pipe type to be a circular force main for the pipe network right after the lift station.
The only way I can run the analysis is to have an outfall right after the lift station.
How can I include the force main in the Sanitary Sewer analysis?
Or, is it not significant to include the force main in the analysis? The purpose of the project is verifying the size of pipes and the lift station.
Thanks in advance for your advice.
Yoko
Solved! Go to Solution.