Corridor Assembly is offset when creating datum surface

Corridor Assembly is offset when creating datum surface

tlincolnAY44Q
Advocate Advocate
440 Views
2 Replies
Message 1 of 3

Corridor Assembly is offset when creating datum surface

tlincolnAY44Q
Advocate
Advocate

As you can see below, the red line (showing the edge of the datum surface) seems to be offset to the left of my corridor border/assembly (the assembly follows that blue line to the right). I keep trying to see if it is a link code problem yet I haven't been able to find the source of the problem. I am thankful for any advice anyone can give.

 

Shifted Corridor.jpg

0 Likes
441 Views
2 Replies
Replies (2)
Message 2 of 3

tmachado
Advisor
Advisor

Hi @tlincolnAY44Q, set your datum and top surface in the corridor properties to be like this image:

2017-12-29 15_47_09-Corridor Properties - 8th St.png

You will get a better result

 

 


Hope this will help!

Was this answer helpful? If so, please click the ACCEPT AS SOLUTION or the LIKES button

Tatiana Machado
BIM Manager/ Autodesk Certified Instructor
Blog | Twitter | LinkedIn
InfraWorks Ambassador

Message 3 of 3

Jeew-m
Mentor
Mentor

Dear Friend,

In addition to the Machado's suggestions make sure that you have added corridor extent as boundary in the corridor surface boundary. 

 

Thanks



Jeewana Meegahage
Design Engineer
Autodesk Civil 3D Tutorials
Facebook | YouTube | LinkedIn