Hello ACC community. Relatively new user her, but have looked in the documentation and forums for this and can't seem to find the answer I am looking for. Is it possible to have multiple versions of a budget, as a project progresses, the budget gets more detailed. Maybe start with a conceptual budget (or version 1), maybe 10-30 line items. Then as the design progress, say through schematic design, create a schematic budget (or version 2), with more detail, leading ultimately to the detailed budget for the project, version 3, which the team would execute against. I am sure others are doing this somehow, can anyone share how this can be done? I basically want the budget development process (through multiple versions of the budget) to track with or have traceability to the other project development and versioning processes. Thanks in advance.
Solved! Go to Solution.