Hi @Ahmed.Mok,
Thanks a lot for the timely reply.
I agree with the main reason 2 ("Hide specific Budget items from internal members (only Managers level)"). However, I do not understand the main reason 1 (Separate the budget shared with Owner and budget shared with downstream.).
Usually, there are three types of Budgets:
Budget Type 1: budget-only, such as fee and markups -- shared with Owner.
Budget Type 2: budgets for self-performed work -- shared with Owner and can be tracked by internal Contracts.
Budget Type 3: budgets for subcontracts -- shared with Owner and downstream.
Do you want to assign different permissions for the above three types Budgets to different Cost users?
Thanks and best regards,
Jason Jiang
Senior Product Manager