It would be beneficial to have an option of selecting which weekdays work is being performed, in the activity template from 360 Plan. Right now it is set up so that work is being performed 7 days per week, which messes up the schedule when it is being imported.
It is obvious that a personal workaround can be made, but it'd be nice to have it implemented in the template from the go.
Plan has a project setting that controls the work schedule for the project. The Project Admin can set this to 5 days a week, 7 days a week or whatever is the standard for the project.
Each individual activity has the option to over-ride that schedule if it needs to be active on a non-working day.
I am working on setting up a project in BIM360 Plan and would like to set up a 4-day work week, M-Th, as the default.
Currently, I only have the option to do 5, 6, or 7 day work weeks. Can you help me out with this?