This was first posted in Newsreader but did not appear in the web browser....
Martin,
Being able to automate the process is why most of us use ACE. As I suggested
to Darren, until a better way to do it comes up, try grouping the drawings
together in sequential order that will have consecutive sheet numbers. The
from the update dialog box, check Sheet and Resequence sheet with "1-01" for
your starting point (assuming "1" is the section number and "01" is the
sheet number. Then check project wide and only highlight the group of
drawings you want to resequence. Check "Process v" and then "OK". This will
generate the sheet numbers for that group. Then repeat for each subsequent
group.
This may not be the best way but at least you will be able to automatically
generate the sheet number values.
Let me know if this makes any sense.
Bob Hanrahan
Ace User since 1998
If this answered your question, please click on "Accept Solution"