I am not able to get a proper connections (Mitre and End Plate splice) for the U220 which is of 400mm. Please find the image for your reference.
Solved! Go to Solution.
Solved by Rob_Merriman. Go to Solution.
Solved by Rob_Merriman. Go to Solution.
From looking at your picture it seems you have 2 sections of U220 at the top of the staircase, 1 of them is already mitred into the landing U220 and 1 of them isnt. If you do a selection window over the U220s above the splice connection i think you will find a clash between both of them
It would be easier to find out the issue if you could upload the model or part of the model.
Rob Merriman, AEC Technical Lead, Graitec
Did you find this post helpful? Feel free to Like this post.
Did your question get successfully answered? Then click on the ACCEPT SOLUTION button.
Hi @Rob_Merriman,
As you have said, the U220 is colloiding with the two connections, As U220 is not taking over the the connection's need. There are many connections as such but for this small length U220, the connections is not been taking over. Please find the model for your reference.
So looking at your model you have 2 UPN channels on top of each other, the mitre and the end plate splice are associated with 1 of the channels, the other needs deleting as you cant have 2 channles on top of each other.
See screencase for explanation - https://autode.sk/3nuuHMu
Rob Merriman, AEC Technical Lead, Graitec
Did you find this post helpful? Feel free to Like this post.
Did your question get successfully answered? Then click on the ACCEPT SOLUTION button.