Concrete Fill for Frame: Volume Calculation

Concrete Fill for Frame: Volume Calculation

Jonathan.CharltonE35Y2
Contributor Contributor
1,287 Views
3 Replies
Message 1 of 4

Concrete Fill for Frame: Volume Calculation

Jonathan.CharltonE35Y2
Contributor
Contributor

Hello,

Specs:
Advance Steel 2022 for Windows 10, 64bit;
Product Version 26.0.605.0 Advance Steel 2022.0.3 Hotfix;
Built on: S.191.0.0 AutoCAD 2022.1.5


Question:

Is it possible to subtract the shapes of profiles/plates from a concrete slab that encases them?

I have a pump frame that will be filled with concrete after installation on-site, and I'm trying to show in my model what that concrete would look like and how much it will weigh.
Thank you in advance for your time and input.

Please see attached .dwg for example.


0 Likes
Accepted solutions (1)
1,288 Views
3 Replies
Replies (3)
Message 2 of 4

Flies-Eyes
Advisor
Advisor
Accepted solution

The short answer is yes, this is possible. The long answer is it could take a while to set up your system to achieve this requirement.

 

We moved away from using the 'Concrete Objects'  to model concrete elements some time ago in favour of using plate elements to model concrete objects. This gave us far better control over numbering, assemblies, single parts and BOMS.

 

Below are some screen grabs of how our Advance Steel system handles concrete BIM data.

 

Concrete Assembly Drawing

FliesEyes_0-1741314696711.png

 

 

Concrete Single Part Drawing    

FliesEyes_1-1741314733273.png

 

Concrete BOM

FliesEyes_2-1741314767134.png

 

I have also included a set drawings of where these concrete element drawings would sit if in a full set of drawings.  

I did a test to push your model to Revit as well.

 

 

Message 3 of 4

Jonathan.CharltonE35Y2
Contributor
Contributor

@Flies-Eyes,

Thank you very much for this information>
I'll chew on this for a little while and see how it might benefit our workflows.

Message 4 of 4

Flies-Eyes
Advisor
Advisor

Having another look at your original post, I used 'Concrete Precast' for the material type as I initially thought your frame was a precast mould.  Being that you call it a 'Pump Frame', I should have used our 'Concrete Insitu' prefix. We treat the data slightly differently, precast concrete the weight is more important as lifting is highly likely, whereas with Insitu Concrete, surface area is more important. 

0 Likes