Hello,
We are looking for a way to add a fixed value to a calculated total in a schedule. Is there any way to do this in a formula in which this value is not added to every single instance?
Thanks in advance.
Solved! Go to Solution.
Solved by ToanDN. Go to Solution.
Yes, it involves using the percentage parameter to add a fraction of the value in question to each instance so that the result = the original total + the required value. I might be able to give you a sample file later.
if I understood well your desire....then it will can be done as follows:
https://www.youtube.com/watch?v=EWsbu_DOB0U
Constantin Stroescu
Thanks for your reply. This adds 1.50 to every single instance. I'd like to add a fixed value to your value 1499.25. in my project we have a lot of unique schedules, and we would like to add a fixed value to the calculated total of them.
Try this sample file assuming you need to add 3' to the total. Unhide columns and look at their formula.