Message 1 of 2
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report
Hi, I am concerned about the fundamental period in my model, it is a frame steel project with truss beams, it is 15 m high and with two offices buildings attached, the thing is that my fundamental period shows 2.46 seconds, and I consider that is too high for my project
I also use braces to reduce the period but instead of reduce it, increase it
So I come here to hear some ideas of what I could make wrong
Thanks beforehand
Solved! Go to Solution.