Message 1 of 1
Schedule Filtered by Sheet and Assemblies
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report
Hi!
When I create a schedule inside an assembly and edit it, I have the option to choose between "by assembly type" and "by assembly instance", as shown below, aside the "Calculate totals" field:
Is there a way to have this option for standard schedules? Because I use a standard schedule that is filtered by sheet (second image below) to sum all rebars of the elements placed in this sheet, and when I have an assembly with more than one instance, I detail and place it on the sheet only once so consequently the totals of the schedule come out wrong, hence it counts only the assembly instance that is placed in the sheet and not all of them existing in the project.
Thanks in advance!