Piping Schedule based on System

Piping Schedule based on System

Furquan_A
Contributor Contributor
502 Views
4 Replies
Message 1 of 5

Piping Schedule based on System

Furquan_A
Contributor
Contributor

Hello everyone.

 

I am looking to generate a Piping Schedule Pipe and Pipe Fittings separately, based on System type can I get Material name into both schedule  which assign into Piping Systems? 

fahemad_0-1650885027379.png

 

0 Likes
Accepted solutions (1)
503 Views
4 Replies
Replies (4)
Message 2 of 5

iainsavage
Mentor
Mentor

You want to include the material assigned to the pipe System in the pipe schedule rather than the actual pipe material - is that correct?

Sounds like a job for Dynamo

0 Likes
Message 3 of 5

Furquan_A
Contributor
Contributor

Thanks for replying @iainsavage .

I am looking to get schedule based on material weather it actual pipe or additional parameters (prefer to automated instead Dynamo to avoid each file and regular), but that has to come in both schedule, pipe schedule and pipe fittings

 

0 Likes
Message 4 of 5

iainsavage
Mentor
Mentor
Accepted solution

I am not very skilled with Dynamo but the attached script seems to do what you want for pipes.

It gives a warning in the last node, but still functions.

If this is the sort of thing you want I could develop it to do pipe fittings too (maybe).

Anyone else with more Dynamo skills please feel free to jump in if you have a better solution.

 

iainsavage_0-1651097078060.pngiainsavage_1-1651097128845.png

 

0 Likes
Message 5 of 5

Furquan_A
Contributor
Contributor

@iainsavage  Thanks for you suggestion