I am responsible for making the coordination drawings for a health science education building. I have the architcture's Revit file, the Structural file and the MEP file. The Mechanical engineer's sized the duct and all that jazz, but it is running into some beams and I have to move some of that stuff around as we are the subcontractor installing the Mechanical and Plumbing systems.
I have tried to linking into a new project with a company template that I created, but when copying the duct work all the systems were lost. Is there anyway to copy those things without losing the systems that are assigned in the MEP model?
Right now, i am working in a model that was opened in the MEP model and linked in the arch. and struct. model. All I really have to do is move around the MEP systems a little bit so everything jives. The problem now is that I cannot manipulate the visibility graphics of any already created views unless i create a new view template. This is getting rather time consuming. and i have made the worksets editable, but i cant override VG's.
Has anyone else ever had to do this same thing for coordination drawings? Is there a suggested workflow as far as what file to open it from or how to set up a project like this for the purpose of coordination drawings?
Thanks