If I'm in a workshared model and I update one of the link from a collaborator, let's say the structural model. What happens if I don't do anything? Do other people's model get update when:
For example we have 6 models for a project internally, all using the structural model. Do I have to go in all these model, manually reload it and synch? What happens if I don't? When will users get the latest version?
Gelöst! Gehe zur Lösung
Gelöst von SteveKStafford. Gehe zur Lösung
Linked Files are reloaded during the open sequence, creating a Local File, or when Manage Links > Reload is used. Linked files are not reloaded for other users during a Synchronize with Central.
If a workset that a link is assigned to is closed the link will be loaded when the workset is opened. If the link has been replaced/updated prior to opening the workset the person opening the workset should see the latest state of the link file.
Steve Stafford
Did you find this post helpful? Feel free to Like this post.
Did your question get successfully answered? Then click on the ACCEPT SOLUTION button.
Hi @SteveKStafford, I have an evolved version of this question.
What happens when working in BIM 360 Design if I update a linked file. Actually, if I consume the package for a linked file. I am asking because in BIM 360 there is no longer a concept of a local and central file.
So if a user opens the BIM 360 file in the morning, will the link update themselves?