so i’ve been modelling a 20 storey building with waffle slabs and tried both beam system and component/void extrusion methods. the first one made my file super heavy and kinda unworkable with my quarantine equipment. while, in the second, i was unable to copy and paste it entirely, since the floor was copied, but not the void extrusions.
do you guys know any solution?
thanks anyways
Gelöst! Gehe zur Lösung
Gelöst von Ahmed_Muharram. Gehe zur Lösung
Why not 2 Beam Systems in the x and y directions, use the Join Geometry tool to join beams at intersections -- and then Group the 2 systems together?
try to remove beam system before replicating the story
Ahmed Muharram, B.Sc, AEE, ACI, ACP
BIM Manager