Hello!
In Revit 2025 I've created one toposolid with some sub-divisions. Let's say that the main toposolid is grass and sub-divisions are pavements. Now I want to calculate the area of the remaining toposolid, of how much grass I have left, without sub-divisions, but the schedule gives me the total area only. In a way - it makes sense, but I would like to have the green area calculated. It was the feature I was using in Revit 2023 and earlier.
Is there any solution to do so? Or a solution would be to create a grass sub-division?
Gelöst! Gehe zur Lösung
Gelöst von barthbradley. Gehe zur Lösung
Unfortunately, no. You will need to manually calculate the area of each subdivided surface.
A resposta te ajudou? Não esqueça de curtir e aceitar como solução!
Vitor Bortoncello | Arquiteto | Especialista BIM
Autodesk Certified Professional
What about just sub dividing the remainder? Should be easy/quick enough using pick lines tool. No?
I had the same solution in mind but was hoping there would be even an easier one, without a need to create separate sub-divisions. Looks like there's no alternative to calculate the partial area straight from the toposolid, though. Thanks for the answers @barthbradley and @vitorbortoncello !