Hello,
1_Can anyone help me about how to combine the stairs with upper floor slab.. ( pls check attached file - no:1 ) I couldnt connect the landing concrete with the stair concrete part, stair concrete should be extended and joined to slab. Also same problem in the bottom slab connection ( pls check attached file2 - no:3 )
2_How can we cut the wall plaster in the connection of landing..( pls check attached file - no:2)
Thanks..
Gelöst! Gehe zur Lösung
Gelöst von kgetev0711. Gehe zur Lösung
Stairs are a separate component so unless you are able to join the to the slab, they often times appear as shown in your screenshot. You can integrate drafting components in order to show it more accurately or use the linework tool: LW to hide the separating line. Select the invisible line type before clicking.
Stairs cannot join to anything, not even the other stairs.
You either use Linework tool to clean up the join conditions, or export the stairs to SAT, then imported it back inn project as an in-place component and join it to other building components.
You should edit the stair first, because as is the top riser looks taller than the rest. ![]()
Thanks I fixed using filled region + masking region.. I tried to fix by LW but its not working in the boundary of filled/masking region... With LW couldnt fix every part of it.