Hello all,
I am currently working on updating my schedules.
For my timber faming I have made my own familiy which contains a wooden column with the possibility of slanted top-edges. Therefor I have inserted a Length parameter.
I have made a schedule which contains 2 columns....
1. the length of the standard wooden columns (field is called Cutlength)
2. the length of the slanted columns (field is called lengteschuineregel)
What I would like to do:
1. make a new Length column which contains the lengthe of the standard or slanted columns.
What I have done:
1. In Schedule Properties I inserted a new calculated parameter called TOTAL
2. selected FORMULA
3. selected Discipline: Common
4. selected Type: Length
5. Formula: IF(Cutlength>0,Cutlength,lengteschuineregel)
The result is.......
In the column TOTAL the only values I see is the Cutlength (as suspected at the standard columns) or it is blank where it should have put the length of the slanted columns....
I need help to fix this item..... ![]()
@kantoor wrote:
In the column TOTAL the only values I see is the Cutlength (as suspected at the standard columns) or it is blank where it should have put the length of the slanted columns....
I need help to fix this item.....
Is the Calculated Parameter set to "Calculate Totals" under the Formatting Tab?