I created a schedule for room area totals by floor levels. I see that the 1st level total is correct but not the 2nd level. The 2nd level seems to be calculated the 1st level instead. How can I correct this?
Gelöst! Gehe zur Lösung
Gelöst von ToanDN. Gehe zur Lösung
I've checked the "itemized" box and unchecked it as well. Does not change anything.
@JKspace424 wrote:
I've checked the "itemized" box and unchecked it as well. Does not change anything.
I didn't suggest checking or unchecking the box would fix it. Is the image you posted from when the box is checked or unchecked?
Wait a minute. I gave it a calc and the result is 1,640. So 1,642 should be correct given some rounding happening. How did you come up with 1,462?
Sie finden nicht, was Sie suchen? Fragen Sie die Community oder teilen Sie Ihr Wissen mit anderen.