Hey all revit masters,
I have an issue projecting a proper numbering in the sheet schedule. By logic, sheet numbers should either increment or decrement, and here I have an issue where it doesn't follow the increment order and it goes as 01,02,03,05,04... I tried looking into filtering options and having other guesses, but nothing is in my knowledge to find a solution to this issue and making the sheet schedule going the proper order like this: 01,02,03,04,05... If you know what could be the issue, please let me know. I will leave a screenshot of the schedule so it would be more clear
Oh, sorry, I thought I attached a screenshot.
Here it is
The sorting and grouping is done with folders and phases, it doesn't really specify on drawing number. You can see it in the screenshot
What year of Revit are you using? I'm unaware of any bug that would do this. The only possibility would be if any other sorting categories are pushing it to go above the sheet number. Look at those values.
If nothing else, make a new schedule and only sort by sheet numbers and see if that shows up correctly, then slowly start adding the other filters.
Sie finden nicht, was Sie suchen? Fragen Sie die Community oder teilen Sie Ihr Wissen mit anderen.