Revit not calculating quantities correctly
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report
Revit, a BIM software, doesn't calculate quantities for material takeoff correctly. Test it. Create a brick wall 0.2×1×1 meter. Volume is 0.2 cubic meters.
Now slap a concrete column through it. Or two, or three. Revit still reports volume of that brick wall as 1 cubic meter.
To get the correct volume you have to join those elements. I'm sure you all know how many structural columns and beams are there, even in an average size building. A massive waste of time and so many opportunities to mess something up.
You may say just subtract one from the other. Nope. There can be a ton of those that are partially inside of walls and ceilings so that wouldn't work.
Revit really should be smart enough to know that two objects can't occupy the same space at the same time. Especially when those objects are a d*mn brick wall and a concrete column.
How do you deal with this?