Revit 2020 - Keynote schedule issue

Hello - We have a running list of user keynotes that are separated by two types: Demolition Keynotes, and Remodel Keynotes.  

 

I would like these to populate into the same schedule, with the demolition keynotes appearing first and the remodel keynotes appearing after the entire demolition list.  

 

The demolition keynotes are alphanumeric and start with a "D".   D1, D2, D3, etc.

the remodel keynotes are numeric: 1, 2, 3, 4, etc.

 

Is there a way to accomplish this in Revit 2020? If we let the schedule run as normal, the numberic (remodel) keynotes appear before the demolition (opposite of what I want). Thanks in advance!

Beschriftungen (2)
4 ANTWORTEN 4
Nachricht 2 von 5
barthbradley
als Antwort auf: keith_hansell

can't you get there by sorting/grouping ascending/descending?  

Nachricht 3 von 5
Lachlan-JWP
als Antwort auf: keith_hansell

Is there a reason you can't use two schedules?

Nachricht 4 von 5
keith_hansell
als Antwort auf: Lachlan-JWP

Yes, this ended up being what I did...just thought there may be a more simple solution.

Nachricht 5 von 5
keith_hansell
als Antwort auf: barthbradley

This didn't work. If I reverse sorted, the numbers would be descending order.