I have a rebar schedule using the default field/parameter "Quantity".

The quantities it is calculated are coming from area reinforcement. I have it sorted by rebar type, then by bar length.

So my schedule looks like:

22    10M    xx"
20   10M    xx"

4    10M   xx"

 

I wanted to add a calculated parameter that would show the rebar per face of the wall. So I thought I'd make a calculated parameter that just divides the Quantity field by 2, but it doesn't calculate right. It would give me:
blank for the 22 total

5 for the 20 total

and 1 for 4 total

 

Why might this be happening?

0 Likes
Accepted solutions (1)
369 Views
2 Replies
Replies (2)
Message 2 of 3

ToanDN
Consultant
Consultant
Accepted solution
Did you format the calc field to calculate total?
0 Likes
Message 3 of 3

Anonymous
Not applicable

Well I feel like a dummy. So many little settings to get used to. Thank you, I appreciate the help.