Revit Architecture Forum
Welcome to Autodesk’s Revit Architecture Forums. Share your knowledge, ask questions, and explore popular Revit Architecture topics.
abbrechen
Suchergebnisse werden angezeigt für 
Anzeigen  nur  | Stattdessen suchen nach 
Meintest du: 

Paint vs Material in schedules

4 ANTWORTEN 4
GELÖST
Antworten
Nachricht 1 von 5
ConstantineC
567 Aufrufe, 4 Antworten

Paint vs Material in schedules

If I have a wall with an interior finish layer of Plywood but then I partially split the face and  paint it as Gypsum Board for example, will the panted area be subtracted from the Plywood quantity take off or will I have both the whole Plywood and the Gypsum board? 

I suspect its the latter?  Is there another way of spliting a wall finish for material take offs other than using parts and spliting them?

4 ANTWORTEN 4
Nachricht 2 von 5
alan.johnson7YLND
als Antwort auf: ConstantineC

Splitting the face and applying paint will give you as you said "the whole Plywood and the Gypsum board"

 

revit split paint.PNG

 

If you Edit Type for the wall,  split the layer and assign a material then you will get a different result 

 

Revit split wall.PNG

 

 

Nachricht 3 von 5
barthbradley
als Antwort auf: ConstantineC

Pull the "Material: As Paint" Parameter into the Schedule.  

Nachricht 4 von 5
ToanDN
als Antwort auf: ConstantineC


@ConstantineC wrote:

If I have a wall with an interior finish layer of Plywood but then I partially split the face and  paint it as Gypsum Board for example, will the panted area be subtracted from the Plywood quantity take off or will I have both the whole Plywood and the Gypsum board? 

I suspect its the latter?  Is there another way of spliting a wall finish for material take offs other than using parts and spliting them?


Paint both areas with different materials: original and paint.

 

ToanDN_3-1682015945019.png

 

 

ToanDN_2-1682015905896.png

 

 

ToanDN_1-1682015793915.png

 

 

ToanDN_0-1682015654917.png

 

Nachricht 5 von 5
ConstantineC
als Antwort auf: ToanDN

So another way is to schedule just the paint. Probably this is how its done in a conceptual stage for early estimate?

Sie finden nicht, was Sie suchen? Fragen Sie die Community oder teilen Sie Ihr Wissen mit anderen.

In Foren veröffentlichen  

Autodesk Design & Make Report