how to adjust this project basepoint to 1st storey level with affecting the value of 1st storey level.
Gelöst! Gehe zur Lösung
Gelöst von ToanDN. Gehe zur Lösung
Hi,
Move the project base point to 1st storey level.
In tab Manage -> Coordinate -> Specify Coordinates at Point and click the Project Base Point. Put the 1st storey level elevation.
If my post help you, please give a like.
If your question was answered please mark it with ACCEPT SOLUTION. This helps others to find answers...
Kostas Kouris
Architect Engineer, M.Sc., ACI, ACP
Move the survey point to the same Elevation as the project base point. Edit the level type to use the survey point for Elevation base. Move the project base point to where you want.