We are working on a master Revit file that has 6 years of phases in it and the owner has hired us to generate 3 new projects that involve new TI's in the existing building. These projects construction will start at varying times. We have begun our preliminary layouts based on the owner's original order, but that order has now changed. Is there any way to move the order of the phases in Revit?
We assume that is not possible and have the following question. The majority of the work we have done to date is demolition and all new items have been mostly mass models, filled regions or area plans. If we were to merge a phase with the previous phase would all demolished elements revert back to existing, or would it simply change it to demolished in the previous phase? Would all the new elements move to new in the previous phase? We assume if we merge it with the next phase that all the demolished walls would be deleted but not sure about that either.