Moving a Revit-model and maintaining the Coordinate System

2 ANTWORTEN 2
Antworten
Nachricht 1 von 3
VH___
335 Aufrufe, 2 Antworten

Moving a Revit-model and maintaining the Coordinate System

Hi!

I am working on a project which will contain various Revit-models for several buildings and multiple disciplines, the project will also be working in different softwares, Plant 3D, Tekla, etc. and who knows what softwares will be developed while the project is ongoing.

 

They want to be able to move around buildings during the project, at all times, including when the design has come very far and drawings have been made. The way I saw the approach was to set up a Site-model and link every Revit-file into this one with Shared Coordinates System, and then move the link and push back the new coordinates to each corresponding Revit-File. This makes the moving and coordination between the Revit-files simple, and also possible to coordinate inside of i.e. Navisworks, with global coordinates.

 

However, this "changes" the Internal Origin and Project Base Point inside the original Revit file, and makes linking the Revit-IFC into, for example Tekla, or other coordination programs such as Solibri, difficult, when all Revit-models will have different Internal Origins and Project Base Points.

 

So the other approach is for the designers to "simply" move all the elements and objects inside of Revit (and other softwares). 

Does anyone have a better solution to this? At the moment the "solution" is that all the designers will move the objects inside their software, instead of messing up all the Internal Origins because that may cause more headache further down the road.

 

Alt. 1, Move the coordinate system which "moves" the building in coordinates, may cause difficulties linking IFC-files

Alt. 2, Move the elements inside of the models, highly likely to cause a lot of problems, but will be fixed with time(?)

Alt. 3 ?????

I would really appreciate some opinions on this!

2 ANTWORTEN 2
Nachricht 2 von 3
barthbradley
als Antwort auf: VH___

I don't understand how the Internal Origins or Project Base Points of the Links are being affected in this workflow (e.g. Linking and Publishing Coordinates from Site to the Links).  Shared Coordinates only involves the Survey Point. On top of that, the Internal Origin is fixed.  It cannot be moved. Nor can the location of the Project Base Point in a Link be changed from the Parent Project.  

 

You have me scratching my head here.  

Nachricht 3 von 3
barthbradley
als Antwort auf: VH___

What about setting up multiple Default Named Sites in the Parent Project (e.g. Site) - each being the Default Insertion Point for a Link? In other words, each Link would have its own Named Site/Survey Point in the Parent Project. Then when you move its Named Site Survey Point, the Link will move with it without affecting the Link-Survey Point relationship.   

 