I have doors in several models that are being linked into another model. The doors are being scheduled in the model they are linked in to. One of the linked models doors are missing in the schedule. I already checked it to be visible in the schedule and to include linked elements, but no success. Please help.
Gelöst! Gehe zur Lösung
Gelöst von SteveKStafford. Gehe zur Lösung
Its the same phase as the schedule. I do have a couple design options in the linked files. But all the doors are showing appropriately in all the files with design options, its just this one link.
Is the missing door assigned to a Design Option that is not a Primary Option?
Steve Stafford
Did you find this post helpful? Feel free to Like this post.
Did your question get successfully answered? Then click on the ACCEPT SOLUTION button.
Yes, but all my doors that aren't assigned to the primary design op in there respective models are showing.
@cgambleTFFSQ can you provide the revit file with just the link that is not showing correctly?
-Rich
What filters do you have in your schedule - is this not preventing it from showing?
Is it not a curtain wall door? These don't show in a door schedule.
It initially appeared that all the doors regardless of design option were showing but that was not the case. I was looking in the wrong place. I checked the vg for all the links and were set to automatic so it was only showing the primary. Thanks.
Sie finden nicht, was Sie suchen? Fragen Sie die Community oder teilen Sie Ihr Wissen mit anderen.