Revit Architecture Forum
Welcome to Autodesk’s Revit Architecture Forums. Share your knowledge, ask questions, and explore popular Revit Architecture topics.
abbrechen
Suchergebnisse werden angezeigt für 
Anzeigen  nur  | Stattdessen suchen nach 
Meintest du: 

Material Scheduling Incorrectly

2 ANTWORTEN 2
Antworten
Nachricht 1 von 3
Shaiki_
241 Aufrufe, 2 Antworten

Material Scheduling Incorrectly

Hi,

 

I have a scheduling error where Revit is not providing the material volume I am expecting. My manual calculations are different than what the schedule is providing. 

 

Im trying to schedule the concrete volume of a precast insulated panel, where we have 3" of concrete, 4" of insulation, and then 3" of concrete. The two concrete wythes need to be scheduled seperately, because there are cases where they are not the same volume. I created two seperate materials for the inside and outside wythe, and filtered the schedule appropriately. From what I can tell, everything is working, just the result is wrong by a little bit. 

 

Ive attached a Revit file with the schedule and wall panels. They are assemblies, and on assembly sheets. Wall 001 seems to schedule okay, but Wall 002 is the one having issues. If anyone could help me find the cause that would be great!

 

Thanks

Tags (2)
2 ANTWORTEN 2
Nachricht 2 von 3
Corsten.Au
als Antwort auf: Shaiki_

wall material.JPGHi

Somehow this part ( Precast Additional ) is affection " Precast Exterior Wythe" Volume which

should not be the case...

Test it.. its withing those two layers and deleting it should not change the volume of Exterior...

but its affecting the volume..

 

Best luck

Corsten
Building Designer
Nachricht 3 von 3
Shaiki_
als Antwort auf: Corsten.Au

Yes somehow the void in the solid family is the issue. Deleting the void fixed the problem, but does anyone know what's really going on?

Sie finden nicht, was Sie suchen? Fragen Sie die Community oder teilen Sie Ihr Wissen mit anderen.

In Foren veröffentlichen  

Autodesk Design & Make Report