How to use formula in schedule for occupant load

4 ANTWORTEN 4
GELÖST
Antworten
Nachricht 1 von 5
gnarkill283
564 Aufrufe, 4 Antworten

How to use formula in schedule for occupant load

I have a default area parameter and a text based parameter for the area per occupant which I manually enter into each areas' properties like so: image.png

I want to now create a formula which takes the area parameter and divides it by the area per occupant to get the load. How does one do this? Thanks

4 ANTWORTEN 4
Nachricht 2 von 5
barthbradley
als Antwort auf: gnarkill283
Nachricht 3 von 5
gnarkill283
als Antwort auf: barthbradley

Thank you and thank god it allowed me to do this with an area schedule because room one wouldn't have worked, but I need the occupant load to round up no matter what the decimal amount is so .1 = 1 person. How can I do this?

Nachricht 4 von 5
gnarkill283
als Antwort auf: gnarkill283

I somehow got this to work: https://forums.autodesk.com/t5/revit-architecture-forum/round-up-calculated-total-of-revit-schedule-... HURRAY!!! Maybe an architecture based program could include this ****!

Nachricht 5 von 5
barthbradley
als Antwort auf: gnarkill283

You can format the parameter values on the format tab.  