Hi in a renovation setting with phasing (and phasing filters) there are different sections of wall adjoining each other:
- existing wall
- infill wall
- new wall
when I place a door in "new construction phase" if it overlaps walls sections of different phases it can only host on
one of them and doesn't cut the other. Any tips on how to solve this?
see wall sections:
trying to place a door which is overlapping 2 phases:
door only cuts one wall :
New Door overlapping New Wall and Existing Wall should cut both and infill both. Are you sure everything is Phased correctly (e.g. Phase Created and Phase Demolished)?
Select the door and you will see the option Pick primary host. Use it to pick the toggle the host and the door will cut all existing, new, infill walls.