When i copy and paste a group from one project to another, I can't get the detail groups to paste in along wiht it.
I also can't paste in the detail group after the fact.
What might I be doing wrong?
Try saving out the detail group and then loading it back into another project file. Right click on Group in Project Browser to save out. Insert / Load from Library / Load as Group to bring the group back in.
Regards Peter.
Hi!
how are you doing the procces?
select the model and detail group and use copy to clipboard
then paste from clipboard or ctrl-V
or as @Pshupe reccomend you save as a group and load in the desired project
Gustavo Ubriaco Contreras
Did you find this post helpful? Feel free to Like this post.
Did your question get successfully answered? Then click on the ACCEPT SOLUTION button.
@svalente9GJKH wrote:
When i copy and paste a group from one project to another, I can't get the detail groups to paste in along wiht it.
I also can't paste in the detail group after the fact.
What might I be doing wrong?
It can be done very simply:
- highlight the model group in the project browser, right click and copy to clipboard
- go to the other project view, open any view or sheet, and paste clip (CTRL+V), the model group and its attached detail group will show in the Project browser for you to use