In the demolition plan, i have already demolished some existing walls, which showing the dash lines.
but in the existing plan, i could not change this dash lines wall into the solid line, which represents the existing wall.
Does anyone know how to figure it out?
see the screenshort below, the first one is demolition plan, and the second one is the existing plan. The demolished wall in two plan should be different. the first is dash line, the second should be solid line.
Gelöst! Gehe zur Lösung
Gelöst von wisedrawing. Gehe zur Lösung
Gelöst von ennujozlagam. Gehe zur Lösung
Gelöst von syman2000. Gehe zur Lösung
Change the phase filter to show complete and those demo should appear as solid in the existing phase.
If you don't have that phase filter, you should add that to the phase to the list where new and existing show by category and demo & temp will not show.
you duplicate the view as dependent?
Apart from the wisdom previously stated, maybe a real obvious one?
Check each sheet/view for Phase filters , just because you are in an 'existing' sheet/view (as labelled) does not mean that its set to existing etc.
I often find I have been swapping phases in a sheet/view during design and have existing as 'show all' or 'new construction' etc.
also sometimes I find I set the wall in existing but as a new wall or visa versa when I was in another phase setting or sheet view (like proposed) and then I am deleting a new wall which shows up different as you are demolishing something created in a different phase.
check the existing is just existing
sorry if that's too obvious
maybe post a shot of the properties panel and the phasing as it matches the demo and existing views??
Thank you guys, i solved this problem with your advice, including using phase filter. i think all of these is very useful!