Have a project in construction with many drawings already issued.
But as I go along and make changes, I cloud these changes so they are ready for a future issue.
These "pending" revisions are then automatically added to the title block, and I mark them as "not issued" until such time as all the work is done and I'm ready to release the revision.
But:
Often a trade will request the latest "unofficial" CAD so they may update their shop drawings.
I then need to send the trade a .pdf and .dwg drawing that shows the previous official revision title and date, even though the drawing may be slightly different.
Up to now I have managed this by manually changing the date and deleting the "not issued" revision notes in the cad and pdf, but I am hoping there is a better way of hiding the future or pending revision note from the Revit title block.
Solved! Go to Solution.