I have a few doors that are only reading one room in the schedule, not both rooms. The line where the other room should be is blank. I have checked the following:
Has anyone run into this before? I have seen this in a handful of instances in the past but was somehow to get things to work. This time I can't get anything to work to show the missing room information. I have had to manually place text on the sheet to fill in the information. Not ideal. Thank you.
Yes I dealt with this all the time. One way to overcome this is to use the room calculation point inside your door family. This will work if the door swing is set to one direction. If you have room that need to flip to other side, then you have to create new family and have the room calculation point to go from one side to another
If this doesn't work, then you have to use calculated value in the schedule to override the room value.
The walls are the typical 5" walls used throughout the project. I would prefer not creating new families just due having to activate the calculation point. We are trying to standardize our doors and creating new ones just for this rare issue could muddy the waters.
Any chance the phase of the missing room is a prior phase or is in a linked model?
Steve Stafford
Did you find this post helpful? Feel free to Like this post.
Did your question get successfully answered? Then click on the ACCEPT SOLUTION button.