When something changes, coordination review highlights the change
but sometimes i can not accept the difference
for example, if a floor boundary changed, it tells me but the options are do nothing, postpone, ignore.
If a level name changed, the options are, do nothing and postpone.
What is the reason behind all this? Thank you
Hello,
Is your project a workshared one?
If my answer solved your problem , Please Kudo and Accept as solution.
Thanks
Hello,
Revit states a phrase about this specific question which says"The available action values vary depending on the type of change" so there is no other reason
for showing some actions and hiding others.
If my answer solved your problem , Please Kudo and Accept as solution.
Thanks