I have concrete ground beams running into the side of a concrete lift shaft wall (pit). The 2 beams at the bottom left are close and want to mitre together but I want the hatched red volume on the screenshot not to occur. I have tried split, and cut (I couldnt select the shaft wall as a cutting element so it doesnt work), can anyone advise on how to get the two beams to stop at the face of the shaft rather than protrude through it?
[img]https://i.imgur.com/L0rh748.png[/img]
Gelöst! Gehe zur Lösung
Gelöst von MichaelWarwick7522. Gehe zur Lösung
Opening by Face using the top of the beams - since this is at a join you will have to do the same opening on both and ignore the 'opening partially cuts host' pop-up.
.