I will try my best to explain this, we are working on a property with a gable end wall, the gable end wall is going to be coming part down and an extra story built on top. We have the existing property drawn up and the walls on an existing phase. Now i have come to draw the new construction what is the practice?
A) Draw up a new wall over the top of the existing wall but on a new construction phase from the base of the wall to the new level. The problem with this method is all the doors and windows which are staying are hosted on the existing wall construction.
B) Do i set a new level above the existing wall and then click into the wall profile and get the base line to match the outline of the gable wall, The problem with this method i will be left with a line where the new wall meets the old.
I would be interested to hear how others tackle the issue of part of the wall being on one phase and part of the wall being on a new phase. Thanks