I'm trying to add 1 1/2" space in between 2 datums halfway through a project while keeping everything associated with the level. I need to add 1.5" space between a top of wall datum and a level but when I move the datums it deletes everything on the level and I cant access the sheet. Any way to move a level without everything being deleted?
What sort of objects get deleted - Dimension, tags? I run into this issue. Only way to work around this is to create a new level 1 1/2" above the level and hide the existing level. Then move the objects to the new level.
So I have a T/O foundation wall datum and a T/O 1st floor and its 9 7/8" and I need to add 1.5" to that but when I picked my T/O FDN wall and footing datum and moved it down 1.5", it would delete all foundation walls and everything on the sheet, including the sheet (basement view was no longer in project browser)
Though I just now tried changing the elevation using the dimension string rather than move tool and it worked without removing it all. Thanks for the reply regardless
It is hard to know what is causing the level delete itself. Share the file so we can take a look.
Go to an elevation and place a dimension between the two levels. Then select the level you want to move and change the value of the dimension. If you want to manually move the level then DO NOT check Disjoin box.