Revit Architecture Forum
Welcome to Autodesk’s Revit Architecture Forums. Share your knowledge, ask questions, and explore popular Revit Architecture topics.
abbrechen
Suchergebnisse werden angezeigt für 
Anzeigen  nur  | Stattdessen suchen nach 
Meintest du: 

Can't Duplicate Schedule - Duplicate View Grayed Out

7 ANTWORTEN 7
GELÖST
Antworten
Nachricht 1 von 8
chrisF633G
612 Aufrufe, 7 Antworten

Can't Duplicate Schedule - Duplicate View Grayed Out

I have a schedule which we are using as a Code Matrix (from the project template). All of the parameters in the columns are project parameters in the "Parts" category and are just Text data.

 

I want to duplicate this schedule so that I can remove some of the rows of content, from the version that appears on the sheet, but not loose that data from the project entirely incase I want to pull it back (irrelevant code sections/ zoning etc). When I right-click the schedule in the project browser and go to "Duplicate View" all of the sub-options for this schedule are grayed out, whereas for the door schedule the first option for "Duplicate" is available.

 

Is there something that would prevent the duplication of a schedule? I don't believe it is a key schedule, but I'm not sure how to tell if it is.

Beschriftungen (3)
7 ANTWORTEN 7
Nachricht 2 von 8
ToanDN
als Antwort auf: chrisF633G

Is it a key schedule? Key schedules can't duplicate.

Nachricht 3 von 8
chrisF633G
als Antwort auf: chrisF633G

@ToanDN is there a way to tell if it is a key schedule? The original version of the schedule came from the template. There are other schedules which I know to be key schedules, but only because they are labeled as such. I can't see anything else in the properties or project browser that identifies a key schedule vs regular schedule. 

Nachricht 4 von 8
chrisF633G
als Antwort auf: chrisF633G

Comparing the type in the properties - the Code Matrix schedule which I can't duplicate is the same type as the door schedule which I can duplicate. (SCHEDULE)

The known key schedules are a different type. (SCHEDULE 1)

Nachricht 5 von 8
ToanDN
als Antwort auf: chrisF633G

- sorting the schedule in the browser can distinguish key schedules and component schedules

- if you see insert row then it is a key schedule or asheet index, notba component schedule

- and, if you can't duplicate then it is a key schedule

Nachricht 6 von 8
chrisF633G
als Antwort auf: chrisF633G

Thank you @ToanDN. It sounds like it's a key schedule in that case since the reason we are using this type is for the insert row function. I think I have an inkling of why they can't be duplicated, but it doesn't entirely make sense.

Nachricht 7 von 8
ToanDN
als Antwort auf: chrisF633G

You can copy the key schedule and paste it into a new project model to keep the original.  Then modify the one in the working project.

Nachricht 8 von 8
ToanDN
als Antwort auf: chrisF633G

You could also create a new key schedule for a different category, but you would need to add all parameters and data from scratch.

Sie finden nicht, was Sie suchen? Fragen Sie die Community oder teilen Sie Ihr Wissen mit anderen.

In Foren veröffentlichen  

Autodesk Design & Make Report