it is adding some unnecessary calculation to my quantities schedule..
Thansk!
I don't understand the issue. You say the Building Pad is slightly higher than the top of the Toposurface. So what? Also, how does this mess with a Schedule? A Schedule of what? Topography? The Pad and the Topo are two separate Categories.
@barthbradley The pad is at the correct level, which is aready dug, but the toposurface is starting a tiny bit under it, which adds 0,02 m3 to my schedule instead of being a clean zero..
@tareqathamneh6QW84: I don't want to play guessing game anymore. Post your file here and I'll tell you exactly what's going on and what to do about it.
@barthbradley here is the file, thanks, I appreciate it.
there are no layers in the pad..
Solution is posted in Message #6.
Set the Pad's Height Offset from Level to ZERO.
@tareqathamneh6QW84 wrote:
I did, still there.
The topo itself already has 0.203 m3 Cut without the pad. Did you create it using Graded Region?