Assign Levels to a Phase

3 ANTWORTEN 3
GELÖST
Antworten
Nachricht 1 von 4
IMCornish
314 Aufrufe, 3 Antworten

Assign Levels to a Phase

I am working on a conversion of a building and some of the Levels of the existing building will not be used in the completed building whilst new Levels will be used, but how do I get rid if the existing levels, that are not being used, in the New Construction drawings? Surely "Hide in View" is a little crude and does not have the automatic nature of a phased project, also meaning that a view may have a level wrongly remaining by accident!

Any ideas? Thank you

Andrew Robertson
Chartered Architect
Robertson Partnership
Truro. UK
3 ANTWORTEN 3
Nachricht 2 von 4
ToanDN
als Antwort auf: IMCornish

Name the levels with (E) prefix and create filter to hide levels with that prefix in new phase views.

Nachricht 3 von 4
IMCornish
als Antwort auf: IMCornish

Smacks a little of a workaround but good enough for me.

Thanks ToanDN

Andrew Robertson
Chartered Architect
Robertson Partnership
Truro. UK
Nachricht 4 von 4
barthbradley
als Antwort auf: IMCornish

Two different Level Types. Make them graphically distinguishable from each other as well (e.g. different Line Pattern, Symbol).  

 

Use whatever Filter method works best (e.g. Selection, Rule-Based, By Element).

 

Create/apply View Templates.   

 

 