2019 scheduling rooms from linked model using level from main model

we have linked models in our main model and we are scheduling the rooms from the linked models. in the schedule it references the level from said linked model i.e. level 1. we want it to schedule these rooms on the level they are on in the main model i.e. level 2,3,4,5.

1 ANTWORT 1
Nachricht 2 von 2
SteveKStafford
als Antwort auf: jledgewood409

Revit won't reference the host model's level because the rooms are not hosted by that level. Only rooms in your host model will be based its levels. Try including the RVT Link information in the schedule to help organize the rooms.


Steve Stafford
Did you find this post helpful? Feel free to Like this post.
Did your question get successfully answered? Then click on the ACCEPT SOLUTION button.
EESignature

Sie finden nicht, was Sie suchen? Fragen Sie die Community oder teilen Sie Ihr Wissen mit anderen.

In Foren veröffentlichen  

Autodesk Design & Make Report